Avenue Road and Eglinton – Final Configuration 

May 3, 2023 


The final configuration at the Avenue Road and Eglinton Avenue intersection.

This also includes all traffic movements, number of lanes, and dedicated turns:

North side of intersection:
o   Two (2) southbound through lanes
o   Two (2) northbound through lanes
o   One (1) southbound left turn lane
Same as pre-construction

South side of intersection:
o   Two (2) southbound through lanes
o   Two (2) northbound through lanes
Same as pre-construction

West side of intersection:
o   Two (2) westbound through lanes
o   The curb lane now has a bicycle lane included
o   Three (3) eastbound through lanes
Same as pre-construction

East side of intersection:
o   Two (2) westbound through lanes (at the intersection)
o   Two (2) eastbound through lanes
One (1) lane less than pre-construction due to bicycle lane inclusion

 

News


UPtown Yonge and Mother’s Day Event – May 11/24

The UPtown Yonge BIA is hosting its 2nd celUPbrate Mom event ...

Stormwater Charge and Water Service Charge?

The City is considering charging for stormwater drainage ...

Castle Knock and Eglinton … 19 Storeys?

There is a proposal to build a 19-storey building

Vacant Home Tax – Declaration BY Feb. 29, 2024

Every year owners of properties must ...

EGLINTON PARK- Master Plan Phase 1 Implementation Update

City's survey closes January 5/24 ...