Avenue Road and Eglinton – Final Configuration
May 3, 2023
The final configuration at the Avenue Road and Eglinton Avenue intersection. This also includes all traffic movements, number of lanes, and dedicated turns: North side of intersection: South side of intersection: West side of intersection: East side of intersection:
o Two (2) southbound through lanes
o Two (2) northbound through lanes
o One (1) southbound left turn lane
Same as pre-construction
o Two (2) southbound through lanes
o Two (2) northbound through lanes
Same as pre-construction
o Two (2) westbound through lanes
o The curb lane now has a bicycle lane included
o Three (3) eastbound through lanes
Same as pre-construction
o Two (2) westbound through lanes (at the intersection)
o Two (2) eastbound through lanes
One (1) lane less than pre-construction due to bicycle lane inclusion